Project finance is facing its greatest external threat for many years. Despite being less risky than lending to corporates it is penalized by the new Basle capital accord (Basle II). As it stands, Basle II will fundamentally alter the structure of the market. A greater polarization will occur between price makers and price takers, and non-bank players will grow at the expense of banks unable to qualify for advanced status. Over the long term, the project finance market has the potential to grow disproportionately when compared with commercial banking as a whole and in theory should represent an attractive proposition for banks looking for balance sheet income.
Demand is set to greatly outstrip supply. The vast market for infrastructure projects in the emerging markets, huge growth in renewable energy, and the expansion of the private finance initiative concept in the developed economies – for everything from toll roads to airports and from schools to hospitals – show no signs of slowdown. According to financial services strategy consulting firm Oliver, Wyman, there will be global demand of $2 trillion to $3 trillion in the next five years compared with total global funding of around $1 trillion in the past five years. Few commercial banking segments offer comparable growth prospects.
After the Latin American crisis in the 1980s, commercial banks’ interest in the developing countries waned, a situation repeated after the Asian crisis of 1997, which is reflected in the chart of global project finance volumes. In the late 1990s there was a strong upturn in interest fuelled by the growth of the telecoms market (driven primarily by the huge investment in 3G and UMTS licences). Telecoms became the biggest industry user of project finance funding – as well as an even bigger user of vanilla corporate debt. In 2001 there was a further slowdown as the technology bubble burst and prospects for 2002 look worse still, with telecoms in particular falling away sharply.
Emerging-market project financiers are, however, used to cyclical markets and even in difficult conditions well-priced and well-structured transactions with strong sponsors can be financed. Moreover, support packages from sponsors and offtakers can be enhanced to improve risk mitigation.
Market participants consistently report lower default rates and, especially, lower loss rates on project financings than equivalent corporate loan exposures, largely because of the effect of transaction structuring and transparency and control of cashflows and collateral. However, there is little public data on project finance default and loss rates, and each individual bank’s internal default and loss experience is relatively thin. Oliver, Wyman’s experience suggests that average loss rates of 0.5% to 1% for developed economies and 1% to 2% for emerging markets are comparable to corporate experience.
In addition, prices have been increasing in recent months, particularly, for example, in the US energy market where competition for project assets is markedly less than in Europe. The knock-on effects of Enron have led several energy companies to reduce leverage and anything that even hints at off-balance-sheet financing, further raising prices. Oliver, Wyman estimates that the risk-adjusted return on capital (RAROC) for project and asset finance is, at between 15% and 35%, among the highest available in wholesale lending, compared with around 10% for vanilla lending.
Yet despite excellent growth prospects, lower loss rates, superior risk-adjusted returns and strong demand, project finance appears to be misunderstood by senior bank management and the aggregate amount of capital applied to it remains relatively small. Why should this be so?
One reason springs from the fact that most banks lack the performance metrics required to demonstrate clearly the value of project finance portfolios on a risk-adjusted basis. Banks have invested large sums in the past five to 10 years in improving internal credit rating systems. However, for understandable reasons, the bulk of this has been directed at the core businesses of middle market corporates, which tend to dominate banks’ risk-weighted assets.
The most common approaches to corporate credit rating use combinations of financial factors (balance sheet and profit&loss) and non-financial factors to predict a probability of default. The choice of factors/values can be based either on internal experience of defaulting and non-defaulting clients (good/bad analysis) or, for large corporates, based on external ratings (and the observed default rates). Other approaches, such as KMV Credit Monitor, use the share price as a proxy for asset values to predict distance to default.
These approaches, and the transparency they bring, are starting to transform plain-vanilla lending, enabling banks to be more informed (and, it’s to be hoped, more disciplined) about pricing for risk, and to sell down loans to end investors (such as insurance companies and loan investment funds). Moreover, they are used by banks (with the increased blessing/encouragement of regulators) to determine the amount of risk that a bank is bearing.
None of these approaches is, however, readily applicable for project finance, because of several characteristics of typical transactions.
First, borrowing entities are often special purpose vehicles, often with limited or no recourse to a sponsor or group of sponsors, which in turn are responsible for different parts of the transaction. So there are no historical balance sheets, P/L statements or share prices to analyze – except when assessing the financial strength of sponsors, off-takers and guarantors.
Secondly, the sponsors’ support beyond their contractual obligations is often more dependent on willingness to pay rather than ability to do so.
Thirdly, loan repayment is made possible by the cashflows generated by the project itself.
Finally, specific mitigating elements are often put in place to maintain cashflow and debt service coverage levels. These are specific to individual transactions and often also apply only to specific events or risks. As such, their inclusion in a structure may serve to reduce the probability of default rather than act as collateral in the event of default. For example, a guarantee in a power plant financing may be callable in the event of fuel supply disruption but not in the event of default for any other reason.
Cashflow is crucial
Probability of default in project finance, and indeed most of the analytical work conducted during the underwriting process, is based on cashflow generation. Put simply, default occurs when cash is insufficient to cover contractual debt service obligations. In practice, this may be at a level that is greater than 100% because of covenant packages and/or may not be classified as default because of debt service coverage breaches in a single repayment period.
Consequently, project finance departments typically find it difficult to provide credit departments with a concise, transparent, objective risk rating that can be compared with simpler transactions on a like-for-like basis.
A second reason why project finance appears to be misunderstood by senior bank management results from a lack of convergence between common corporate rating systems and assessment methods used by credit risk departments and the cashflow-based analysis typically undertaken by project financiers. This leads many credit risk departments to assume that high complexity always equates to high risk.
Put simply, credit departments often don’t understand project finance transactions. This is because they are, by their nature, complex and require a strong understanding of the underlying markets and their risk drivers. Only a limited number of banks have dedicated project finance credit teams with individuals who can debate the risk of a transaction with the front office from a position of equal knowledge.
As a result, for many projects only the originator truly understands the cashflows (and thus the risks) involved, creating a potential “gamekeeper/poacher” problem whereby the one person able to rate the project is the one who benefits from a favourable rating.
As a result, credit departments, and senior management, sometimes feel it is safer to steer clear of structured deals – which, ironically, often have the highest RAROC. This issue prevails not just internally but also externally, where the secondary market for project finance is thin. Lack of risk transparency doesn’t help.
Senior bank managements have also probably been unduly swayed in their assessment of project finance deals by headline-hitting high-profile default cases, such as Bangkok Mass Transit and Eurotunnel. A bank CEO would rather explain away an up-tick in domestic credit losses that has also affected all his peers than a single big hit on, say, a power station in a little-known central Asian republic. However, well-structured project finance transactions tend to lead to lower loss-given-default (LGD) experience than equivalently rated corporate debt because the complexity of the financing structure is matched by a mitigation structure that deals with each key element of risk and its impact on the cashflow generation of the project.
Conversely, as recent events have amply demonstrated, unsecured corporate lending exposes the lender to all the risks of the corporate, including the empire-building tendencies of “rock star” CEOs, without mitigation of any of the key risk drivers.
Despite these challenges, several banks have been working hard in the past 12 to 18 months on developing transparent rating systems for project finance. These break project finance portfolios into sub-portfolios with common risk drivers: for example, for power projects, gas, electricity or coal prices, fuel supply disruption and off-taker default. Given plausible assumptions for key risk drivers (for example, volatility of gas prices), the ratings are then built around simulating cashflows and debt service coverage for individual projects. These simulations can then determine probability and loss distribution and directly observe the impact on cashflows and riskiness of a particular transaction structure under different market environments.
The parameterization of the rating simulations combines market data and expert judgement in a structured way that allows transparency and consistency in risk evaluation without losing the ability to capture the specifics of a transaction’s structure. While one model is not sufficient for all types of projects, the same core methodology and set of principles can be applied, with different risk drivers and parameterization, to different sub-portfolios, such as power, wind and telecoms.
The simulation-based rating systems have met with very positive feedback from project finance specialists, credit departments, senior management and bank supervisors. They offer a credible approach for objective risk assessment of complex projects, assisting banks in moving away from the situations where the originator alone is able to validate the rating of transactions, itself a Basel II requirement. As such, these tools provide a basis for both internal risk monitoring and control and regulatory capital attribution.
The impact of Basle II
In October 2001, the models task force of the Basle Committee published its working paper on specialized lending. In this paper, specialized lending is defined as project finance, object finance, income-producing real estate and commodity finance.
Adoption of this paper would have a substantial adverse effect on an already misunderstood industry.
In line with many of the comments above, the working paper takes as its starting point the assumption that project finance is riskier than corporate lending.
The internal ratings based approach for specialized lending has two proposed levels: the foundation approach and the advanced approach.
The foundation approach is characterized by supervisory probability of default and LGD pair estimates and, in turn, risk weights. The indicative risk weights as set out in Table 1 in the amended foundation approach for project finance are under consideration. The advanced approach is where the institution estimates all expected loss parameters from its own experience.
Use of the foundation approach would lead to much higher capital charges than today and make all but the strongest project finance transactions uneconomic from a capital perspective (see Table 2). For example, at best, incomplete projects will receive a “fair” rating, while stress LGD and exposure at default may well be as high as 100%.
The advanced approach offers a lifeline to the project finance industry. In order to meet the requirements of this approach, banks individually and the industry as a whole, need to convince the regulators (as well as senior management) that the risk of project finance as an asset class really is misunderstood.
The requirements under the advanced approach fall into two main categories. First, transparent, consistently applied internal rating systems for project finance transactions. Second, sufficient internal data on defaults and losses to calibrate rating systems and determine loss given default. Both face significant hurdles.
Basle II provides a further challenge through Pillar II requirements, which require specialist internal rating teams and a clear distinction between the origination and rating functions.
Many observers, including most notably the rating agencies, argue that it is extremely difficult to construct a single rating framework within which all projects can be analyzed. The standard response from the industry is that every transaction is unique. This is patently not correct and in addition it does nothing to help the case of the industry in the eyes of regulators, credit departments, senior management and investors.
For most banks, default and loss data is an industry-level issue. Very few banks have sufficient internal project finance defaults and losses to develop robust LGD estimates in line with Basle II requirements, especially when portfolios need to be segmented by industry and/or geography to make such estimates relevant.
Citigroup is coordinating a multi-bank study of defaults and losses from project finance loans. The first phase of the study reported on recovery experience from the four initial participant banks in March 2002 and the intention is to provide the Basle Committee and national regulators with evidence of the misperception of the true level of risk in project finance.
As written, the Basle II requirements could lead to a number of adverse changes for the market as a whole.
| Table 1: Indicative risk weights | |
| Supervisory rating category | Indicative proposed risk weight |
| Strong (BBB- up) | 75% |
| Fair (B+ to BB+) | 150% |
| Weak (B or worse) | 300% |
| Default | 750% |
| Table 2: Approximate capital charges using the foundation approach | |||
| Supervisory class | Risk weight | Approximate external rating category | Approximate capital charge |
| STRONG | 75% | BBB – or better | 6% |
| FAIR | 150% | B+ to BB+ | 12% |
| WEAK | 300% | B | 24% |
| DEFAULT | 750% | D | 60% |
| Table 3: Impact on the industry | |
| Arranger/maker | Providers/takers |
| ? Fees and net interest margin (NIM) | ? NIM only |
| ? Cherry-picking of best transactions | ? Asset and price taker |
| ? Off-loading of less attractive transactions | ? Balance sheet hold strategy |
| ? More sophisticated risk measurement capability | ? Less sophisticated risk measurement capability |
| ? Lower capital charges | ? Higher capital charges |
| ? Leverage to attract best market skills | ? Reduced skills leverage |
Accelerated polarization
The likely consequence of the current guidelines is a polarization (see Table 3) of the project market into arrangers of finance (price makers) and providers of finance (price takers). This is already happening to a large extent in the market, with several arranging banks reducing sharply. Basel II can only serve to accelerate this polarization. Indeed, it may already be a factor in this trend.
Some banks have already decided privately to exit the project finance business altogether. However, they have significant run-off portfolios and Basle II’s introduction will still have an impact since the banks will be caught in a dilemma between uneconomic investment to comply at advanced level, or higher capital charges, or trying to sell the portfolio). Others are likely to follow if (as is often the case) internal Basle II compliance programmes leave specialized lending businesses at the back of the queue for internal rating developments.
In addition, the Basle II rules will create significant barriers to entry for new market participants. Regulatory capital charges will be punitive for non-advanced players and the significant risk management and data requirements for advanced market participants suggest long transition times to advanced status for new entrants.
There is a strong likelihood that new entrants will predominantly be non-banks, especially those that have a cross-sell advantage or pricing leverage, eg the capital goods manufacturers themselves.
The withdrawal of funding providers has important consequences for the overall liquidity of the market, especially in the higher-risk segments involving emerging markets or new technologies. A fully functioning project finance market needs both big and small players. In theory, they should all have the capability to analyze the risk of transactions accurately, even if their underwriting and structuring capabilities are limited. In practice, they will have to under Basel II.
The major international players are not immune to these effects. Not only do many banks have a long way to go in improving the transparency of their internal rating systems but any reduction in liquidity because of market exit by smaller players will have clear knock-on effects.
Alternative sources of liquidity are not readily available, even if the funding techniques are, without greater transparency and investor confidence in the underlying market. Banks that have attempted to put together pure project finance (and other specialized lending) securitizations have found the size of the first-loss tranche demanded by the rating agencies to be prohibitive from an economic standpoint. A small number of collateralized loan obligations have been constructed but such transactions are usually included as a small percentage of larger corporate securitizations. Liquidity will lag behind vanilla lending significantly until such time as project finance assets can be analyzed with much greater transparency.
The consequences of the foregoing are clear. There will be a further deepening of the misguided view that project finance is a marginal activity for banks with a higher than average risk profile and there will be a contraction of the market driven by the onerous requirements of Basle II. Another consequence will therefore be a reduction in liquidity and a greater reliance on supranationals, development banks and ECAs to fund project finance, especially in emerging markets. A contracting market and more rigorous capital requirements also imply that there will be upward price pressure on transactions.
Although Basle II might have compounded the misperception issue surrounding project finance, the solution is not simply to castigate the Basle Committee for getting it wrong. The industry needs to look inwards for most of the solutions.
Market participants big and small need to invest in appropriate risk measurement approaches that transparently demonstrate the relatively attractive risk/return profile of the industry for senior management and credit departments. Only then will a greater share of bank capital be assigned to project finance and supply and demand allowed to converge.
The industry needs to make a concerted efforts to convince regulators and others of the true risk profile of project finance, through better risk measurement, pooled data collection efforts and open dialogue. Failure to do this could lead to a mismatch between regulatory capital requirements and economic reality, which could simply promote regulatory arbitrage and a move away from project financing by regulated financial institutions. Significant contraction in the number of regulated project finance players would certainly not send a positive message to the secondary markets, whatever the underlying rationale.
Arrangers and funding banks need to find more liquidity by promoting appropriate risk transfer vehicles, demonstrating the attractiveness of the asset class to institutional investors and accelerating the change from a buy-hold mentality to a more active portfolio management approach.
Paul Ashley is a director of consultants Oliver, Wyman&Company